Planning, design, and construction services for canals, pipelines, check structures, box culverts, pump stations, ground water wells, small hydro-electric power plants and related works.
Concrete canal lining with wire mesh reinforcement. Tie in work done during a 7 day water outage for the Yuma Mesa Irrigation and Drainage District.
New spillway and turnout structures for Yuma Irrigation District's South Gila Canal at Avenue 3E. Due to ADOT's reconstruction of the I-8 and Avenue 3E traffic interchange, Avenue 3E was widened and YID's existing canal and turnouts needed to be relocated.
Flow restored to canal after tie in to the new box culvert. Irrigation flows through the realigned YMIDD A Canal at Avenue 7-1/2E and Business Route 8. A new and longer box culvert and channel lining was completed to accommodate ADOT's widening of the highway.